Construction updates November 2017 Block B – The Ocean Suites

Dear Valued Customers,

VinaCapital Danang Resort Ltd would like to send you the latest construction update for VinaLiving’s condominium project in Danang known as ‘The Ocean Suites’:-

  • Site Infrastructure:
  • Installation of storm water and electrical services now completed.
  • Road, car parking, footpath has been completed.
  • Generator room has been completed.
  • Street light has been completed.
  • Fence construction has been completed.
  • Building Works
  • Internal and external painting work completed in October 2017.
  • Installation of timber floor, aluminium doors and timber doors completed in October 2017.
  • Steel door installation completed in October 2017.
  • Interior fit – out completed in October 2017.
  • Lift installations completed in October 2017.
  • The signage on the building B and entrance has been installed.
  • Landscape:

- Landscape of common area and around building has started in October 2017 and completed in November 2017.

  • Delivery:

-  Handover remains on schedule by end of December 2017.

 

Best Regards,

 

1. The Ocean Suites signage completed

 

Picture1

 

 

Picture2

 

 

Picture3

 

2. Tower B signage completed

 

Picture4

 

Picture3

 

 

3. Corrugated iron fence completed 

Picture5

 

Picture6

 

4. Landscaping works completed 

 

Picture12                                                           

 

Picture8

 

 

 

5. Front, Rear, Side elevation 

 

 

Picture10

 

 

 

 

 

Picture11

 

Picture9

 

 

6. Aerial view

 

Picture12

 

Picture13