CONSTRUCTION UPDATE SEPTEMBER 2017 BLOCK B – THE OCEAN SUITES

Dear Valued Customers,

VinaCapital Danang Resort Ltd would like to send you the latest construction update for VinaLiving’s condominium project in Danang known as ‘The Ocean Suites’:-

  • Site Infrastructure:
  • Installation of storm water and electrical services now completed.
  • Road and car parking works: aggregate completed and prepare to pave asphalt concrete.
  • Generator room has been completed.
  • Building Works
  • Internal painting work completed from level 4 to level 9 with level 1 to level 3 now underway.
  • External painting work is ongoing (from level 1 to 9).
  • Installation of timber floor completed from level 3 to level 9 with level 1 to 2 now underway.
  • Installation of aluminium doors and timber doors completed from levels 2 to level 9, with level 1 now underway.
  • Steel door framework(s) installation completed from level 4 to level 9 and ongoing from level 1 to 3.
  • Installation of steel handrail to stair exits and glass handrail completed in September 2017.
  • Interior fit – out completed from level 3 to level 9 with level 1 to 2 now underway.
  • Lift installations now underway. Power connection completed and testing is ongoing.
  • Landscape:

- The concept landscape design has been completed with physical works now underway.

  • Delivery:

- Scheduled for handover in the latter parts of Q4 2017

 

Best Regards,

 

1. Internal painting works

 

Level 4~9_Internal painting completed

 

 

 

Level 1~3_Internal painting ongoing

 

 

2. External painting works

 

Level 1~9_External painting ongoing (1)

 

Level 1~9_External painting ongoing (2)

 

 

3. Installation & Completed of timber floor 

 

Level 1~2_Installing timber floor

 

Level 3~9_Timber floor completed

 

 

4. Installation  of timber floor & & Completed alu door-window

 

 

Level 2~9_Completed alu door & window

 

Level 1_Installing alu door & window

 

 

5. Installation& Completed of timber door 

 

 

Level 2~9_Completed timber door

 

Level 1_Installing timber door

 

6. Glass handrail for balcony completed & Steel handrail for stair completed

 

Level 1~9_Glass handrail completed

 

 

 

 

Level 1~9_Steel handrail for stair completed

 

 

7. Installation & Completed of steel door 

 

                                                                                                            Level 1~3_Installing steel door

 

 

 

                                                                                                            Level 4~9_Steel door completed

 

 

8. Installation & Completed of furniture 

 

Level 3~9_Furniture completed

 

Level 1~2_Installing furniture

 

 

9. Generator house_Completed 

 

Generator house_Completed

 

 

10. Infras_Aggregate completed for road and car parking

 

Infras_Aggregate completed

 

11. Công tác hạ tầng

 

DCIM100MEDIADJI_0563.JPG

 

12. Aerial view and Elevation view

 

 

DCIM100MEDIADJI_0558.JPG

 

 

 

Front elevation

 

 

 

Level 1~9_External painting ongoing (1)

 

 

Level 1~9_External painting ongoing (2)

 

 

Side elevation